Events Church Building Progress Report for January 2021 By Parish Communication - February 1, 2021 0 1205 FacebookTwitterPinterestWhatsApp Protective felting, screeding & block works in preparation for back filling ongoing. Removal of scafold from completed 4th quadrant cast & clearing of the ground floor ongoing On-going works including Re-enforcement of the 12 pillars representing the 12 Apostles and form works for staircase in preparation for casting ongoing. Thank you for your generous contributions. TweetSharePinShare0 Shares